Case study
PORR Company
Office Space Renovation
Project data
Name
Lighting Project for PORR Company
Place
11th District, Vienna, Semmering Sector, Austria
Purpose
Office Space Renovation
Year of completion
2023.
Object
PORR AG owns numerous buildings, warehouses, and asphalt plants in the 11th District of Vienna. In 2023, the renovation of a 5,000 m² office space was planned. The project aimed to provide high-quality lighting that enhances the working environment, ensures safety, and promotes energy efficiency.
CHALLENGES
Workspace Flexibility:
Mandatory uniform lighting of 500 lux in offices due to flexible furniture arrangement.
Adapting lighting to different functional needs in offices, corridors, and restrooms.
Technical Requirements:
Installing the main office luminaires (ASTERIX) parallel to the windows and fixing them to the L profiles of the suspended ceiling’s metal structure.
Maintaining aesthetic coherence with the modern interior design.
Energy Efficiency:
Minimizing energy consumption.
Using LED technology for all luminaires.
SOLUTIONS
BUCK provided a lighting solution proposal using products from the BARTENBACH range, with two types of luminaires for the entrance, two for the offices, and two for the restrooms. The proposed luminaires were:
Entrance Luminaires:
Type A and Type B luminaires, designed to provide a warm welcome and secure lighting for entrance areas.
Office Luminaires:
ASTERIX luminaires (ASTERISK 1195/840 DALI RAL9010 3500lm 24W), extended and installed parallel to the windows, fixed to the L profiles of the suspended ceiling’s metal structure.
Ensuring uniform lighting of 500 lux in all offices.
Restroom Luminaires:
Type C and Type D luminaires (SPOTFP LED FIX 8W/4000K), designed for optimal restroom lighting.
Needs Analysis and Planning:
Detailed analysis of the space and consultations with the client to ensure all technical requirements and preferences were met.
Lighting Design:
Utilizing advanced lighting simulations through DIALUX EVO calculations to ensure uniform lighting and efficient light distribution.
Customizing the design of the luminaires to ensure the main office luminaire (ASTERIX) was installed parallel to the windows.
Installation:
Installation of all luminaires according to the plan, with special attention to ensuring ASTERIX luminaires were fixed to the L profiles of the suspended ceiling’s metal structure.
Implementation of daylight and presence sensors to optimize energy consumption.
Testing and Maintenance:
Thorough testing of all installed luminaires to ensure proper functioning and meeting all specifications.
Planning regular maintenance to ensure the longevity and efficiency of the lighting system.
The lighting project for the PORR company office building successfully met all set objectives. Uniform lighting of 500 lux was achieved, allowing flexibility in the placement of workstations. The installed luminaires provided optimal lighting and aesthetics for the space. Energy efficiency was significantly improved thanks to the use of LED technology and smart sensors.
Benefits for the investor
Efficient and modern lighting plays a crucial role in creating a productive and pleasant working environment. The lighting project for the PORR company office building demonstrates how careful planning, advanced technology, and design can lead to outstanding results. The PORR Group expressed great satisfaction with the achieved results and plans to implement similar solutions in future projects.
Share with colleagues and friends
Copy url